Full meaning
African Union
Community of Sahel–Saharan States
Common Market for Eastern and Southern Africa
Economic Community of West African States
Investimento direto estrangeiro
Produto interno bruto
Inclining block tariff(s)
International Monetary Fund
Independent power producer
Kilowatt
Kilowatt hour
Gás de petróleo líquido
Megawatt
Pay as you go
Power purchase agreement
Private public partnership
Standard and Poors Global Ratings
Sub-Saharan Africa
Transmissão e Distribuição
Time of use
West African Economic and Monetary Union
United Nations Industrial Development Organization
Value added tax
World Bank Regulatory Indicators for Sustainable Energy
Um sistema de energia distribuída que produz electricidade num local centralizado a partir de uma ou de uma combinação de fontes de energia distribuida aos clientes finais normalmente através de uma rede de baixa tensão. As mini-redes podem ser isoladas ou interligadas com a rede principal.
Em todos os Country Briefs, um pequeno PPI é definido como qualquer sistema ligado à rede inferior a 10 MW que funcione com base num acordo de compra de energia (PPA), com o único objectivo de alimentar a rede com energia (sem autoconsumo).
SHS são produtos solares fora da rede com capacidades de pico geralmente entre 11 Wp e 350 Wp, que alimentam luzes e outros pequenos aparelhos DC, tais como ventiladores e televisores, que incluem armazenamento de baterias para fornecimento de electricidade fora dos períodos de produção. Os sistemas solares Pico são tipicamente inferiores a 11 Wp, oferecendo serviços básicos de energia, tais como iluminação e carregamento de telemóveis.
Os sistemas de energia cativa são definidos como sendo sistemas "atrás do contador", cujo objectivo principal é o autoconsumo. Estes sistemas podem estar fora da rede ou ligados à rede.
Para efeitos dos Country Briefs, isto inclui fogões de "cozinha limpa", fogões de cozinha melhorados, biogás e sistemas de cozinha a gás de petróleo liquefeito (GPL).
Segmentos de mercado
IPP involvement in Burundi started with the 2015 Law on the Reorganisation of the Electricity Sector, which permits private generation of electricity subject to different regimes (declaration, authorisation, concession and PPP). Following the enactment of the law, the government has signed a PPP contract with Gigawatt Global for the Mubuga 7.5 MW solar plant. Project development commenced in 2015 and commissioning was planned for 2018, but progress was delayed by the political crisis of 2015. Construction commenced in January 2020. Contracts were also signed with a consortium consisting of Tauber Solar and Sarako for the Gitega 10 MW and the Bubanza 10 MW solar projects, but little is known about their progress. The government also entered into PPP agreements with larger IPPs, for example, Swedenergy (Kagu 006 12 MW hydro/solar) and Global Synergy Solutions (30 MW waste).
The prevailing regulatory framework is relatively favourable towards IPPs. Private participation in electricity generation is encouraged and procedures regarding interconnection with distribution and transmission grids, PPP procurement, feasibility study authorisation and construction permitting are provided for. Yet, projects are often delayed considerably, as the case of Mubuga shows.
The prevailing regulatory framework is relatively favourable towards IPPs. Private participation in electricity generation is encouraged and procedures regarding interconnection with distribution and transmission grids, PPP procurement, feasibility study authorisation and construction permitting are provided for. Yet, projects are often delayed considerably, as the case of Mubuga shows.
Regulamentos
Law Nr. 13 of 23 April 2015 on the Reorganisation of the Electricity Sector in Burundi is seen as a milestone for increased private sector involvement. It brings an end to REGIDESO's monopoly in electricity generation. The law permits private generation of electricity, subject to certain conditions. Generation systems above 500 kW require authorisation, while generation systems below 500 kW must only be declared. Hydro projects larger than 1 MW are subject to a concession regime. PPP contracts must be signed if projects are situated on state-owned land.
Decree Nr. 100/130 of June 23, 2016 on the reorganisation of the transmission, distribution and marketing of electricity specifies the authorisation procedure for the construction of transmission and distribution infrastructure and provisions relating to the sale of electricity by independent producers supplying their electricity transmission and distribution grids, quality of electricity and PPAs.
Decree Nr. 100/131 of June 23, 2016 on the generation, import and export of electricity provides for the conditions under which the Ministry can limit or prohibit the generation, import and export of electricity.
Decree Nr. 100/132 of June 23, 2016 on the procedure for the development of a generation plant for exclusive and commercial use requires that the development of a generation plant will commence with feasibility studies authorised by the Ministry, followed by obtaining a construction and operation permit. The decree elaborates on the procedures involved.
Law Nr. 14 of 27 April 2015 on the General Regime of Public-Private Partnership Contracts sets out the procurement and contracting guidelines for PPP contracts. Decree No. 100/31 of 24 February 2017 on the Procedures applicable to the award of PPP contracts elaborates on prequalification criteria, evaluation processes of shortlisted submissions and general guiding principles pertaining to PPP procurement.
Decree Nr. 100/132 of June 23, 2016 on the procedure for the development of a generation plant for exclusive and commercial use requires that the development of a generation plant will commence with feasibility studies authorised by the Ministry, followed by obtaining a construction and operation permit. The decree elaborates on the procedures involved.
Law Nr. 14 of 27 April 2015 on the General Regime of Public-Private Partnership Contracts sets out the procurement and contracting guidelines for PPP contracts. Decree No. 100/31 of 24 February 2017 on the Procedures applicable to the award of PPP contracts elaborates on prequalification criteria, evaluation processes of shortlisted submissions and general guiding principles pertaining to PPP procurement.
Burundi does not currently have many operating mini-grids. This is however starting to change. At the end of 2019, a company named Songa Energy successfully raised funding for a 9 MW solar-hydro hybrid project. Consisting of two plants, this project will supply electricity both to the national grid and to a local mini-grid of 20,000 households.
In 2015 the company ENERSOL, in partnership with Etrave installed the 20 kW Kinyinya Hospital solar system, which was expanded to provide electricity to a local mini-grid. A number of international private sector actors including the Spanish Trama TecnoAmbiental have expressed interest in the market.
In the National Development Plan 2018-2027, the government targets the construction of four solar mini-grids, in Ndava/Ryansoro (25 kW), Gatereni/Gitanga (50 kW), Buheka (25 kW) and Kazirabageni/Nyanza-Lac (50 kW). Least cost electrification planning efforts in Burundi indicate that to reach 2030 targets, one third of energy generation capacity would be most affordably provided by mini-grids. A recent geospatial analysis identified 150 suitable mini-grid sites, at locations that are not expected to be electrified by the grid in the short and medium term.
In 2015 the company ENERSOL, in partnership with Etrave installed the 20 kW Kinyinya Hospital solar system, which was expanded to provide electricity to a local mini-grid. A number of international private sector actors including the Spanish Trama TecnoAmbiental have expressed interest in the market.
In the National Development Plan 2018-2027, the government targets the construction of four solar mini-grids, in Ndava/Ryansoro (25 kW), Gatereni/Gitanga (50 kW), Buheka (25 kW) and Kazirabageni/Nyanza-Lac (50 kW). Least cost electrification planning efforts in Burundi indicate that to reach 2030 targets, one third of energy generation capacity would be most affordably provided by mini-grids. A recent geospatial analysis identified 150 suitable mini-grid sites, at locations that are not expected to be electrified by the grid in the short and medium term.
Regulamentos
Law Nr. 13 of 23 April 2015 on the Reorganisation of the Electricity Sector in Burundi is seen as a milestone for increased private sector involvement. It brings an end to REGIDESO's monopoly in electricity generation. The law permits private generation of electricity, subject to certain conditions. Generation systems above 500 kW require authorisation, while generation systems below 500 kW must only be declared. Hydro projects larger than 1 MW are subject to a concession regime. PPP contracts must be signed if projects are situated on state-owned land. Selling of surplus electricity to the grid is allowed under certain conditions. Generation, transmission and distribution of electricity of capacities up to 1 MW for own use are subject to a declaration regime, while mentioned activities for own use are subject to an authorisation regime if the capacity exceeds 1 MW. The state has a legal monopoly on the main transmission and distribution grid. It can however delegate the construction and operation of isolated grids to non-state entities. This is subject to the requirement of a signed public service delegation contract.
Decree Nr. 100/130 of June 23, 2016 on the reorganisation of the transmission, distribution and marketing of electricity specifies the authorisation procedure for the construction of transmission and distribution infrastructure and provisions relating to the sale of electricity by independent producers supplying their electricity transmission and distribution grids, quality of electricity and PPAs.
Decree Nr. 100/131 of June 23, 2016 on the generation, import and export of electricity provides for the conditions under which the Ministry can limit or prohibit the generation, import and export of electricity.
Decree Nr. 100/132 of June 23, 2016 on the procedure for the development of a generation plant for exclusive and commercial use requires that the development of a generation plant will commence with feasibility studies authorised by the Ministry, followed by obtaining a construction and operation permit. The decree elaborates on the procedures involved.
Law Nr. 14 of 27 April 2015 on the General Regime of Public-Private Partnership Contracts sets out the procurement and contracting guidelines for PPP contracts. Decree No. 100/31 of 24 February 2017 on the Procedures applicable to the award of PPP contracts elaborates on prequalification criteria, evaluation processes of shortlisted submissions and general guiding principles pertaining to PPP procurement.
Decree Nr. 100/132 of June 23, 2016 on the procedure for the development of a generation plant for exclusive and commercial use requires that the development of a generation plant will commence with feasibility studies authorised by the Ministry, followed by obtaining a construction and operation permit. The decree elaborates on the procedures involved.
Law Nr. 14 of 27 April 2015 on the General Regime of Public-Private Partnership Contracts sets out the procurement and contracting guidelines for PPP contracts. Decree No. 100/31 of 24 February 2017 on the Procedures applicable to the award of PPP contracts elaborates on prequalification criteria, evaluation processes of shortlisted submissions and general guiding principles pertaining to PPP procurement.
The standalone solar market in Burundi is in its infancy. Bizisol, Greenbox Solar, ITCO, Little Sun, Nambiar, Solar Links and Virago are among the key actors involved in distributing and selling standalone solar products in Burundi. Yet, no GOGLA and Lighting Global affiliated sales were recorded in 2018 or 2019. As of 2020 the government, in partnership with development institutions, has been planning to distribute standalone solar products to approximately 65,000 households.
This market, currently unregulated, shows extensive untapped potential. Preliminary least cost electrification planning indicates that one third of power capacity in 2030 would have to come from standalone solutions. The market for standalone systems is estimated at two million households.
This market, currently unregulated, shows extensive untapped potential. Preliminary least cost electrification planning indicates that one third of power capacity in 2030 would have to come from standalone solutions. The market for standalone systems is estimated at two million households.
Regulamentos
The market is unregulated. Generally, Law Nr. 13 of 23 April 2015 on the Reorganisation of the Electricity Sector in Burundi is seen as a milestone for increased private sector involvement. It brings an end to REGIDESO's monopoly in electricity generation. The law permits private generation of electricity, subject to a Private Public Partnership regime and authorisation by the Ministry.
The captive power market in Burundi has seen little activity to date, in comparison to neighbouring countries. Enersol and Etrave installed 150 off-grid rooftop solar systems at 40 health centres across eight provinces in 2015. Distributed Power Africa (DPA) is also active in Burundi. Owned by the Econet Group, the company is installing a 104 kW rooftop solar system at the Econet Leo Centre in Bujumbura. The Kamenge University Hospital in Bujumbura operates a 403 kW grid connected ground mount solar array. In terms of biomass, Moso Sugar Company (SOSUMO) operates a 4 MW cogeneration plant powered by bagasse for its own use, with seasonal operations.
There are no regulations focused on the captive power market. General regulations pertaining to electricity generation would thus apply to captive power.
There are no regulations focused on the captive power market. General regulations pertaining to electricity generation would thus apply to captive power.
Regulamentos
Law Nr. 13 of 23 April 2015 on the Reorganisation of the Electricity Sector in Burundi is seen as a milestone for increased private sector involvement. It brings an end to REGIDESO's monopoly in electricity generation. The law permits private generation of electricity, subject to certain conditions. Generation systems above 500 kW require authorisation, while generation systems below 500 kW must only be declared. Hydro projects larger than 1 MW are subject to a concession regime. PPP contracts must be signed if projects are situated on state-owned land. Selling of surplus electricity to the grid is allowed under certain conditions. Generation, transmission and distribution of electricity of capacities up to 1 MW for own use are subject to a declaration regime, while mentioned activities for own use are subject to an authorisation regime if the capacity exceeds 1 MW.
Decree Nr. 100/131 of June 23, 2016 on the generation, import and export of electricity provides for the conditions under which the Ministry can limit or prohibit the generation, import and export of electricity.
Decree Nr. 100/132 of June 23, 2016 on the procedure for the development of a generation plant for exclusive and commercial use requires that the development of a generation plant will commence with feasibility studies authorised by the Ministry, followed by obtaining a construction and operation permit. The decree elaborates on the procedures involved.
Law Nr. 14 of 27 April 2015 on the General Regime of Public-Private Partnership Contracts sets out the procurement and contracting guidelines for PPP contracts.
Decree No. 100/31 of 24 February 2017 on the Procedures applicable to the award of PPP contracts elaborates on prequalification criteria, evaluation processes of shortlisted submissions and general guiding principles pertaining to PPP procurement.
Law Nr. 14 of 27 April 2015 on the General Regime of Public-Private Partnership Contracts sets out the procurement and contracting guidelines for PPP contracts.
Decree No. 100/31 of 24 February 2017 on the Procedures applicable to the award of PPP contracts elaborates on prequalification criteria, evaluation processes of shortlisted submissions and general guiding principles pertaining to PPP procurement.
More than 95% of the population in Burundi rely on burning biomass or solid fuels on open fires or in inefficient cookstoves for cooking purposes. Wood is used by 94.2% of the population. Other fuels include charcoal (5.1%), coal (0.2%) and liquid petroleum gas (LPG) (0.2%). The clean cooking sector in Burundi is limited to a few distribution programmes and a small number of commercial sales. Energising Development (EnDev) has been distributing improved cookstoves via third parties and Vulcanex International has been selling the Vulcanex stove, a smoke-free improved wood stove. Other players in the market include Alfaco Bioenergy, Burundi Quality Stoves and KTF Solutions.
The government is also leading clean cooking programmes. The National School Canteens Programme provides 800 schools across the country with free lunches. Approximately 400 of these schools operate clean and improved cookstoves to serve meals for approximately 500 to 800 children a day. As of 2020, the government, in partnership with development institutions, has also been planning to distribute clean cookstoves to approximately 300,000 households and 400 schools by 2026.
The government is also leading clean cooking programmes. The National School Canteens Programme provides 800 schools across the country with free lunches. Approximately 400 of these schools operate clean and improved cookstoves to serve meals for approximately 500 to 800 children a day. As of 2020, the government, in partnership with development institutions, has also been planning to distribute clean cookstoves to approximately 300,000 households and 400 schools by 2026.